CEGH REMIT platform for publication of inside information

This platform enables market participants to publish inside information according to REMIT Regulation (EU°No.°1227/2011).
The CEGH REMIT Platform is endorsed by E-Control Austria, inside information can be published in English (or in the official language(s) of the relevant Member State and in English) via the CEGH REMIT Platform in an effective manner.
The use of the CEGH REMIT Platform is free of charge. For detailed information please refer to the "Terms of Use"
Filter your results
to
to
Export filtered postings
Export filtered postings
Please choose which posting versions should be included in the download:
20.09.201900:00 CEST
31.03.202400:00 CET
Update to Tyra restart
03.08.2022 07:30 CEST
00048894-21X000000001099X_001 (active)
TotalEnergies EP Danmark A/S
21X000000001099X
Unavailabilities of gas facilities
Other unavailability (planned)
Tyra II (21Z000000000251U)
01.04.202200:00 CEST
31.12.202300:00 CET
Continued early warning level for the Austrian market areas East, Tyrol & Vorarlberg
22.12.2022 12:01 CET
000000048387-A00007693.AT_002 (active)
AGGM Austrian Gas Grid Management AG
A00007693.AT
Other market information

26.09.202219:12 CEST
01.01.202506:00 CET
Offshore pipeline isolated upstream and downstream due to pressure drop
31.03.2023 17:21 CEST
00049138-21X000000001398N_004 (active)
Nord Stream AG
21X000000001398N
Unavailabilities of gas facilities
Offshore pipeline unavailability (unplanned)
GREIFSWALD-NEL (exit) (21Z000000000255M), GREIFSWALD-OPAL (exit) (21Z000000000241X)
01.12.202223:00 CET
30.12.202323:00 CET
Planned interruption, thermal energy not needed
02.12.2022 13:08 CET
000000049466-A0012786X.RO_001 (active)
BIO ELECTRICA TRANSILVANIA
A0012786X.RO
Unavailablilities of electricity facilities
Production unavailability (planned)
Radauti
11.12.202223:00 CET
30.12.202323:00 CET
Planned power reduction
02.12.2022 13:03 CET
000000049464-A00036357.RO_001 (active)
HS Timber Productions
A00036357.RO
Unavailablilities of electricity facilities
Production unavailability (planned)
Radauti II
01.02.202323:00 CET
30.12.202323:00 CET
production unavailability planned
01.02.2023 10:06 CET
000000049616-A00036357.RO_001 (active)
HS Timber Productions
A00036357.RO
Unavailablilities of electricity facilities
Production unavailability (planned)
Radauti II
28.02.202323:00 CET
30.06.202322:59 CEST
Unavailability due to plant outage
11.04.2023 17:40 CEST
000000044933-A0002185D.RO_003 (active)
OMV Petrom SA
A0002185D.RO
Unavailablilities of electricity facilities
Production unavailability (planned)
Combined Cycle Power Plant Brazi (30W-PETR-BRAZ1-W)
08.05.202323:00 CEST
29.09.202323:00 CEST
Lack of thermal load turbine with back pressure
09.05.2023 07:21 CEST
00050117-30XROCOLTERM---S_001 (active)
Compania Locala de Termoficare "Colterm" SA
30XROCOLTERM---S
Unavailablilities of electricity facilities
Production unavailability (planned)
CET South
06.06.202314:00 CEST
15.07.202322:00 CEST
production unavailability planned
06.06.2023 13:18 CEST
00050256-30XROHS-SEBES--B_001 (active)
HS TIMBER PRODUCTIONS SEBES SRL
30XROHS-SEBES--B
Unavailablilities of electricity facilities
Production unavailability (planned)
SEBES 1, SEBES 2
07.06.202307:00 CEST
08.06.202313:00 CEST
Maintenance planned
06.06.2023 13:25 CEST
00050257-60X0000000000559_001 (inactive)
MAZARINE ENERGY ROMANIA SRL
60X0000000000559
Unavailablilities of electricity facilities
Production unavailability (planned)
CHP Dofteana